Construction Quotation

Hunan Mengneng Technology Co., LTD. Painting Construction Quotation table
 Order numbe  Project Process name Material name Brand Dosage
(kg/㎡)
Unit price
(yuan/kg)
Money
(yuan/㎡)
1 Material cost 1、Base surface sandblasting Sand blast       10.00
2、Consumables Construction tools, labor protection supplies       2.00
3、Cold spray zinc coating 2 ways(80μm) Cold spray zinc Mengneng spray zinc cold 0.55 58 31.90
4、Cloenser coating 2 ways(80μm) Cold spray zinc Mengneng spray zinc cold 0.55 58 31.90
5、Fluorocarbon coat 2 ways(80μm) Cold spray zinc Mengneng spray zinc cold 0.55 58 31.90
2 Labour charges Grinding, painting, and repair   /   12.00
3 Measures cost Construction protection, temporary logistics, high-altitude work, skateboard   /   12.00
4 Equipment loss cost Material-level equipment loss 12.00
5 General expenses Office expenses, financial expenses, management personnel wages, labor insurance premiums, travel expenses, transportation expenses, business entertainment expenses, etc 12.00
6 Project profit Project profit 12.00
7 Tax fees Tax VAT 12.00
8 Summation   116.61
9 Aggregate 7800*116.61=909558.00
Quotation description: 1. This table contains 10% project tax, and the quotation period is valid for 20 days
2. Quotation time: On July 29,2018
Quotation unit: Hunan Mengneng Technology Co., LTD